BESS financing benefitting from other clean energy segment struggles, US uncertainty, Fidra CEO says

February 11, 2026 at 9:23 AM
Cameron Murray
Energy-Storage.news Storage_Batteries Batteries & BESS ✓ Processed

Summary

Owner-operator Fidra Energy came out of virtually nowhere to be building one of Europe's largest BESS in the UK, the 1.4GW/3.1GWh Thorpe Marsh project. We catch up with CEO Chris Elder, about its strategy and projects but also broader BESS and clean energy financing trends.

Owner-operator Fidra Energy came out of virtually nowhere to be building one of Europe's largest BESS in the UK, the 1.4GW/3.1GWh Thorpe Marsh project. We catch up with CEO Chris Elder, about its strategy and projects but also broader BESS and clean energy financing trends.

📝 RSS Summary Only
Tags: Features toll financial close ldes gas plants uk long-duration energy storage Interviews EnergyStorageEurope