After years of negotiations, data centers and other large customers of Georgia Power have finally won a pathway to pay for their own new clean energy projects to be built and connected to the utility’s grid. The Georgia Public Service Commission approved the utility’s program last week, allowing these companies to…

After years of negotiations, data centers and other large customers of Georgia Power have finally won a pathway to pay for their own new clean energy projects to be built and connected to the utility’s grid. The Georgia Public Service Commission approved the utility’s program last week, allowing these companies to…