U.S. Solar developer seeks connection to wrong powerline, delays project five years
The OFW Solar Project in Virginia submitted an application to connect to powerlines run by the wrong power company, instead of a second set of nearby transmission lines, necessitating a total restart of the PJM interconnection process that could push construction back to 2032.